We asked nine people when the job started. We received literally 9 different answers for the same exact job.
$4.5 million had already gone into two implementations that never gave Hutton the tools to run the company. Five groups each carried a different construction start date, and the only source of truth was a sprawling spreadsheet guarded by the CEO's right-hand man.
WIP ran weeks off, over and under billings would not reconcile, and a job leadership believed was profitable was quietly bleeding cash. They could not say with confidence which properties they owned or who owed them rent each month.
Nine people gave nine different answers for when a single job started. The reporting was not broken so much as ungoverned: no definition of a start date was owned by anyone, and the Director of Construction, who had the right one, was not the source any system used.
We unified the start date to the one construction actually owned, established governed definitions every system agreed on, and made the prior software spend productive rather than replacing the ERP or CRM.
WIP runs clean on every cycle, and eight departments work off the same numbers instead of five versions of them.